Critical path refers to the sequence of activities that must be
completed on time for the entire project to be completed on time. It is an
important aspect of your project schedule. Here are five things to know about critical
path.
1. Float refers to schedule flexibility
On every project, no matter how complicated, there are always some
activities that can be started earlier or completed later without jeopardizing
the final completion date. This flexibility between the earliest time an
activity CAN be completed and the latest time when it MUST be completed is
called "float".
2. The critical path has no float
Now let’s look at those activities where you do not have the flexibility
in the start and end-dates. These activities cannot be completed earlier
because they are pending the completion of another activity. They also cannot
be completed later without causing all the succeeding activities to be late.
All of these activities back up tightly against other activities that precede
or succeed them. In other words, the path has zero float.
The critical path consists of the longest sequence of activities that
must be started and completed exactly as scheduled. It is the longest sequence
of activities with zero float.
3. Why is the Critical Path Important?
If the project is trending late it is very important to identify the
critical path activities. Unless you are able to accelerate activities on the
critical path, the end-date for the entire project will not change. Applying additional
resources to activities that are not on the critical path will not affect the
overall project end-date. Your chance to make an impact on the projected
end-date relies on your ability to identify and shorten the critical path.
4. The Critical Path May Change
Given that there are many, many paths through the schedule, it’s
possible for the critical path to change. For instance, say you have a project
with 22 activities over nine months. Let’s assume that there is another path of
work that includes 19 activities and takes 8 ½ months. There are two weeks of
float on this path. Let's say one of the activities on the 8 ½ month path ends
up taking an extra four weeks. Because there was only two weeks of float in the
path, it will now become the critical path and force the entire project to
complete in 9 1/2 months.
5. You must sequence activities to understand critical path
The critical path relies on an understanding of the successors and
predecessors of each activity. If your activities are not sequenced, the
critical path may be calculated erroneously.
No comments:
Post a Comment