Freeze Scope Change Requests Late in the Project
The later scope changes occur, the more they tend to impact schedule and
budget. You might think that as long as the sponsor is willing to approve
increases in budget and time to make the change, they should be able to do it.
This is normally true - but only up to a point. There comes a time in a
project where it just doesn’t make sense to make additional scope changes. That
is the time to gain a commitment for a change freeze. Not only are new changes
expensive to implement, they are a distraction to the project team.
Depending on the nature of the project, this freeze is usually implemented
as the team is getting ready for the “drive to implementation”. At this point,
the team is focused on implementing the solution. At that point in the project,
scope change requests are not only costly, but they are also very disruptive.
The team can lose focus and become mentally deflated. You may find that the
next time there is a “drive to implementation” the team will get sloppy and
make mistakes, since this would be the second time they performed these
implementation activities.
The better approach is to hold these changes on a backlog and deal with
them as enhancement requests after the solution is implemented and stable.
Track Valid Change Requests that are not Approved During the
Project
It is possible that the sponsor may not approve scope change requests
during the project, but they may be viable requests that can be done at a later
time. These types of change requests should be captured on a backlog list.
After the project is completed and the solution is moved to the operations and
support organization, there may be opportunities for enhancements or a Phase II
project.
Do Not Use Estimating Contingency for Scope Changes
One of the steps in the estimating process is to add contingency hours,
budget and schedule to reflect the level of uncertainty associated with the
estimate. (For instance, if the effort hours were estimated at 5,000 hours, you
might add 500 hours for contingency, which reflects a 90% confidence factor and
10% uncertainty.) Once the contingency is approved, there will be pressure on
the project manager to use the contingency to absorb additional requirements.
The client might say, “Why do we need to invoke scope change management for
this 100 hour enhancement. You have 500 hours of contingency built into your
estimate!”
The project manager must resist the temptation
and the pressure. The purpose of the estimating contingency is to reflect
uncertainty in the estimates. There will be plenty of opportunities to utilize
the contingency when activities take longer than expected. Do not use the
estimating contingency to absorb extra work.